Solution Overview
Meicheng engineered a complete heavy-haul transport solution including route survey, bridge reinforcement, multi-province permitting, and specialized blade-transport trailers with police escort.
Key Actions
- Route survey and engineering: Conducted a 5-day route survey identifying 23 restricted bridges, 8 narrow village roads, and 12 critical turns; designed bypass routes and reinforcement plans
- Bridge reinforcement: Installed temporary steel support structures on 7 bridges that could not support 25-ton axle loads
- Multi-province permits: Obtained oversized transport permits from Tianjin, Hebei, and Inner Mongolia transport authorities within 15 days
- Specialized trailers: Deployed 3 blade-transport extendable trailers (up to 80m) with hydraulic steering for tight turns and 360-degree blade rotation capability
- Police escort and traffic control: Coordinated with local traffic police for escort vehicles at all 12 critical turns and 8 village passages
- Convoy scheduling: Transported blades in convoys of 3, with each convoy departing at night to minimize traffic disruption