Heavy-haul truck transporting 78-meter wind turbine blade through mountainous terrain to Inner Mongolia

Project Cargo Logistics

Wind Turbine Blade Transport: Tianjin to Inner Mongolia Project Site

A wind energy company needed to transport 12 sets of 78-meter wind turbine blades from Tianjin port to an Inner Mongolia wind farm. Meicheng engineered a heavy-haul route with police escort and bridge reinforcement.

Клиент

North China WindPower Energy Co.

Отрасль

Renewable Energy

Услуга

Project Cargo Logistics

Маршрут

Tianjin Port, China → Ulanqab, Inner Mongolia, China

Тип груза

Wind turbine blades, 78m length each, 12 sets (36 blades), 25 tons per blade

78m
Blade Length
36
Blades Delivered
600
km Distance
38
Days Completed

Задача

Client Background

WindPower Energy was constructing a 200MW wind farm in Ulanqab, Inner Mongolia. They needed to transport 36 wind turbine blades (78 meters each) from Tianjin Port to the project site, a distance of 600 km through mountainous terrain and rural roads.

Key Challenges

  • Oversized cargo: Each blade was 78 meters long, 4.2 meters wide, and weighed 25 tons — far exceeding standard transport dimensions
  • Route obstacles: The 600 km route included 23 bridges with weight restrictions, 8 villages with narrow roads, and 12 sharp turns requiring blade maneuvering
  • Time window: All 36 blades needed to arrive within 45 days to meet the construction timeline before winter
  • Permit requirements: Oversized transport permits were needed across 3 provinces (Tianjin, Hebei, Inner Mongolia) with varying regulations

Решение

Solution Overview

Meicheng engineered a complete heavy-haul transport solution including route survey, bridge reinforcement, multi-province permitting, and specialized blade-transport trailers with police escort.

Key Actions

  • Route survey and engineering: Conducted a 5-day route survey identifying 23 restricted bridges, 8 narrow village roads, and 12 critical turns; designed bypass routes and reinforcement plans
  • Bridge reinforcement: Installed temporary steel support structures on 7 bridges that could not support 25-ton axle loads
  • Multi-province permits: Obtained oversized transport permits from Tianjin, Hebei, and Inner Mongolia transport authorities within 15 days
  • Specialized trailers: Deployed 3 blade-transport extendable trailers (up to 80m) with hydraulic steering for tight turns and 360-degree blade rotation capability
  • Police escort and traffic control: Coordinated with local traffic police for escort vehicles at all 12 critical turns and 8 village passages
  • Convoy scheduling: Transported blades in convoys of 3, with each convoy departing at night to minimize traffic disruption

Результаты

Results

  • All 36 blades delivered in 38 days, 7 days ahead of the 45-day deadline
  • Zero damage to any blade during the 600 km transport
  • All 7 reinforced bridges passed inspection with no structural issues
  • Zero accidents or traffic incidents across 12 convoys through 3 provinces

The wind farm was commissioned on schedule in November, generating 200MW of renewable energy. WindPower Energy has since contracted Meicheng for 2 additional wind farm projects in Hebei and Gansu.

Нужно аналогичное решение?

Расскажите нам о вашей отгрузке, и мы подготовим индивидуальное коммерческое предложение по экспедированию в течение 24 часов.